top of page

Interception
well for P&A operations 
 

with the goal of successful operations, respecting principles that guarantee: reducing operational risk, improving learning, sharing knowledge, increasing efficiency. 
Respecting the environment and safely.

how we it

In order to optimize the stages of the process, Syngular Solutions uses the PDCA methodology to achieve excellence and obtain results in the face of challenges. 

Gráfico Ciclo PDCA Azul.jpg

Plugging problem: damaged cased-well 
 

 A new well was planned and drilled to intercept the original well and open a window on it. The work string was run down the window and the plugging and abandonment operations were done.

1_edited_edited.png

The interception well made it possible to establish a bottom plug and ensured the isolation of the reservoir. Intermediate and surface plugging could be performed by conventional plugging methods.